Intention

The construction phase is when the appointed Accredited Contractor carries out the required works in accordance with the endorsed design plans.

GVW should be advised of a suitable opportunity to attend an on-site pre-start construction meeting.

Key documents

 

Forms for submission

► The Consultant must submit Pre-construction Certification (PDF, 147kb) with a minimum of 5 working days prior to the commencement of any works.

Form: CCTV Sewerage Inspection Notification (PDF, 96kb).

► Form: Sewage Pump Station or Rising Main Shutdown (PDF, 104kb)

Submit all correspondence to mail@gvwater.vic.gov.au.